Runway 17-35 Asphalt Mill, Replace, Re-marking, and Signage Corrections to Runway 18-36
Aviation
Project Description
This project addressed the need to rehabilitate the main runway. This project will include the following: 2 inches of asphalt milling, 2-3 inches of asphalt pavement overlay, runway grooving, runway marking, taxiway taper corrections to Taxiway C, and re-designation from Runway 17-35 to Runway 18-36, as well as signage panel corrections for the runway re-designation and taxiway designation corrections.
Project Description
-
Project Location:
Valdosta Regional Airport (VLD) | Valdosta, GA
-
Project Owner:
Valdosta-Lowndes County Airport Authority
-
Contract Type:
5-Year On-Call Contract
Holt Consulting Company Contributed:
- Concept Development
- Grant Application
- Design
- Bidding
- Construction Administration
- Grant Closeout
Project Highlights
A water table issue during construction caused Holt to have to design an underdrain system for 1,300 feet of the runway during construction. The design was accomplished in a short time frame and the contractor was able to install the underdrain system so the project was able to be completed without major grading and drainage changes to the area.