General Aviation Terminal and Hangar Development Project

Aviation

Project Description

This project provided a new 4,800 SF terminal building and adjacent 11,900 SF storage hangar.  Working with local architects at JMA, the Holt Team designed and bid the previously mentioned buildings in two schedules (A and B).  Due to escalated construction prices from the volatile COVID economy, the project required extensive value engineering and cost negotiations with the contractor to allow a project within the Airport Authority’s budget.  In addition to the buildings, the project included 1,800 SY of new asphalt pavement, access road and parking lot, drainage improvements, and new utilities, including power, communications, water, fire protection and a septic system.

Project Description

  • Project Location:

    Perry-Houston County Airport (PXE) | Perry, GA

  • Project Owner:

    Perry-Houston County Airport Authority

  • Contract Type:

    5-Year On-Call Contract

Holt Consulting Company Contributed:

  • Project Management
  • Design & Bidding
  • Value Engineering
  • Construction Services (Management & Inspection)

Project Highlights

Despite supply chain and cost escalation challenges due to COVID-19, coupled with several Owner requested changes during construction, the entire team delivered the project within 1% of the original budget (industry standard varies from 3%-6%), meaning the overall cost control was outstanding.  This project was recognized at the 2023 Georgia Airports Association (GAA) Conference for the “General Aviation Project of the Year” Award.